Little's Law: cases entering, staying and leavingTen new applications arrive per business day; an average of 200 cases are in the process; a case stays 20 business days, because 200 equals 10 times 20. In a What-if with 150 cases and the same arrivals the cycle time is 15 business days. Illustration not to scale.10 per business dayWork in processaverage 200 casesCycle time20 business days200 = 10 × 20 · What-if: 150 = 10 × 15 (15 business days)Illustration not to scale
Figure. Illustrative example, not to scale: WIP = arrival rate × cycle time, under the assumption of a stable process.

Ten new applications arrive each business day and about 200 cases are in the process on average, so a case stays 20 business days: 200 = 10 × 20. If you know any two of these values, Little's Law can calculate the third. In a What-if with 150 cases in the process and the same 10 arrivals a day, the cycle time is 15 business days. This is an illustrative example, not to scale. Little's Law assumes a stable process, and it does not guarantee that reducing work in process by itself will make the real cycle time fall.

Purpose

Little's Law connects three everyday numbers: how many cases are in the process at the same time (work in progress, WIP), how many new cases arrive per unit of time (the arrival rate) and how long a case stays from start to finish (the cycle time). If you know any two, the third follows. Written as a formula: WIP = arrival rate × cycle time.

How to use this analysis

Little's Law: the workflow in 6 stepsBoxes joined by arrows, left to right: 1. Choose what you know; 2. Confirm units; 3. Confirm source; 4. Calculate; 5. Interpret; 6. Try a What-if.1Choose whatyou know2Confirmunits3Confirmsource4Calculate5Interpret6Try aWhat-if
Figure. Little's Law: follow the numbered steps from left to right. The same steps appear on the page under “How to use this analysis”.

Choose a process and a scenario, enter your values and press Calculate. The result appears immediately below the button and the page moves it into view, so you never have to search for it. Read what it means, then enter a What-if in the What-if step and press Calculate What-if: its result and the comparison with the baseline appear directly underneath. You never have to scroll back up to calculate. Calculate What-if is a temporary experiment: it saves nothing, so you can change the figures and calculate again as often as you like. Choose Save as scenario only when you want to keep that What-if. In a Little's Law What-if, give two figures and the empty one is calculated (the baseline never fills it in); if you fill all three, choose which one to calculate. The page shows these same steps in the same order.

The same moves for every technique: the result appears right under the buttonSeven boxes joined by arrows: 1 Enter values, 2 Calculate, 3 Result appears immediately, 4 Understand the result, 5 Enter a What-if, 6 Calculate What-if, 7 Baseline vs What-if.1Entervalues2Calculate3Result appearsimmediately4Understand theresult5Enter aWhat-if6CalculateWhat-if7Baseline vsWhat-if
Figure. Visual walkthrough: enter values, calculate, read the result that appears right below, enter a What-if, calculate it in the same step and read the baseline against the What-if.

The steps, as they appear on the page

What you need: Little's Law needs any two of: cases in the process, arrival rate, cycle time.

Little's Law: provide two, calculate the thirdThree cards: Cases in the process 200 cases (KNOWN), Arrival rate 10 per business day (KNOWN), Cycle time 20 business days (CALCULATE).Cases in the process (WIP)200 casesKNOWNArrival rate10 per business dayKNOWNCycle time20 business daysCALCULATEYou provide any two. ProcessWeave calculates the third.
Figure. Provide any two of WIP, arrival rate and cycle time. ProcessWeave calculates the third.
Little's Law worked example: 200 cases, 10 per dayThree panels joined by arrows. Step 4: 200 cases and 10 cases per day, press Calculate Little's Law, result: Cycle time 20 business days. Step 6: change cases to 150, press Calculate What-if, result: Cycle time 15 business days. Baseline vs What-if: cases 200 to 150, arrivals no change, cycle time 20 to 15 days.STEP 4 — Calculate200 cases · 10 cases / dayCalculate Little's LawCALCULATED: Cycle time 20 business daysSTEP 6 — Try a What-ifCases in the process: 150Calculate What-ifWHAT-IF: Cycle time 15 business daysBaseline vs What-ifCases 200 → 150Arrivals no changeCycle time 20 → 15 days
Figure. Worked example: the result appears directly under each Calculate button, and the What-if is calculated inside Step 6.

Step 1 — Choose what you already know

Fill in exactly two of the three cards: cases in the process (WIP), arrival rate and cycle time. The empty one is calculated.

Step 2 — Confirm units

Pick the unit beside each figure. ProcessWeave converts everything to one standard unit for the calculation and shows you the conversion.

Step 3 — Confirm source

Say whether the figures are observed, come from records, or are your own assumption. You can leave the reference empty.

Step 4 — Calculate

Press Calculate Little's Law.

Step 5 — Interpret

The result is explained in a sentence, followed by the formula under Show Calculation.

Step 6 — Try a What-if

Change one figure to see what the law suggests. Your baseline stays as it is.

Little's Law assumes the process is stable (arrivals and completions balance over time). ProcessWeave does not check this, so read the result as an estimate if the assumption holds.

Use it to answer questions such as: if we receive 10 requests a business day and each takes 20 business days, how many are open at once? Or: if we want to cut open work to 100 cases, how short must the cycle time be?

Choosing a process

Open the technique from the Process Analysis menu and pick a process in the 'Choose a process' dropdown. It lists only the processes you are allowed to view. If two processes have the same name, the folder after the name tells them apart. Then choose the Open button. Moving to another technique keeps your choice.

Required inputs

  • Exactly two of: WIP (cases), arrival rate (cases per hour, per day or per business day) and cycle time (minutes, hours, days or business days).
  • The working calendar (hours in a business day, business days in a week). A business day is not 24 hours; it uses the calendar stored with the scenario (default 8 hours, 5 days).
  • Values must be zero or above and finite. Dividing by a zero arrival rate or zero cycle time is refused with a message.

Prepared versus manually entered inputs

Little's Law does not need the BPMN diagram to calculate. Every number is entered by you as a scenario value, or taken from a prepared value if one exists in the scenario. Each value keeps its source (for example scenario assumption, observed or calculated) so an assumption is never presented as an observed fact.

InputWhere it can come fromCanonical unit used inside
WIPEntered, or observed count of open casescases
Arrival rateEntered, observed or from a logcases per second
Cycle timeEntered, observed or from Flow Analysisseconds

Step-by-step workflow

  1. Open Process Analysis and choose Little's Law for the process version you want to analyse.
  2. Pick or create a scenario. Check the working calendar.
  3. Enter exactly two of WIP, arrival rate and cycle time, each with its unit. Leave the third empty.
  4. Choose Calculate. The page shows the formula, the numbers substituted in canonical units, the calculated value in a unit you can read, and the assumptions.
  5. Use Show Calculation to see every step. Copy the sentence under Interpretation if you need it in a report.
  6. To explore a change, duplicate the scenario as a What-if, change one input and compare.

Worked BPMN example

A purchase-request process modelled in BPMN receives 10 requests per business day. A review of recent requests shows about 200 are open at any time. Which cycle time does that imply?

  • Calendar: 8 hours per business day, so one business day is 28 800 seconds.
  • Arrival rate: 10 cases per business day = 10 ÷ 28 800 = 0.000347222… cases per second.
  • WIP: 200 cases.
  • Cycle time = WIP ÷ arrival rate = 200 ÷ (10 per business day) = 20 business days (576 000 seconds).

Under this scenario, a case takes about 20 business days from start to finish. If the BPMN lists Duration values for each task, compare their sum along the main path with this figure; a large gap may show waiting time that the diagram does not capture.

What-if example

Keep the arrival rate at 10 cases per business day and ask what happens if process improvements cut the cycle time from 20 to 12 business days.

QuantityBaselineWhat-ifChange
Arrival rate10 per business day10 per business dayno change
Cycle time20 business days12 business days-8 days (-40%)
WIP200 cases120 cases-80 cases (-40%)

This estimate suggests that, if the shorter cycle time were achieved and the same number of cases kept arriving, about 80 fewer cases would be open at any time.

Interpretation

  • Read results as 'Under this scenario...': they describe the long-run average, not any single day or case.
  • If WIP is high for the arrival rate, cases spend most of their time waiting; cycle time can only fall if WIP falls or arrivals slow down.
  • The law does not say a given WIP or cycle time is good or bad. It only shows what the three numbers must be if the assumption holds.

Assumptions

This What-if calculation assumes a stable process.

  • Stable means that over the period considered, cases leave about as fast as they arrive, so the average WIP is not steadily growing or shrinking. ProcessWeave shows this text with every calculation. It does not test it and never blocks a calculation because of it.
  • The three values describe the same process, the same cases and the same period.
  • WIP, rate and cycle time are long-run averages, measured in a consistent calendar.

Limitations

  • No distribution is assumed or used: Little's Law gives averages only and says nothing about the spread, peaks or waiting for a particular resource.
  • It does not find bottlenecks (use Capacity & Bottlenecks) and does not model queues (use Queueing Analysis). The three techniques are independent and do not read each other's results.
  • Exactly two values are required; entering all three is refused rather than checked for consistency.
  • It does not modify the BPMN diagram or any stored process data.

Provenance

  • J. D. C. Little (1961), 'A Proof for the Queuing Formula L = λW', Operations Research 9(3).
  • Dumas, La Rosa, Mendling and Reijers, Fundamentals of Business Process Management, chapter on quantitative process analysis.
  • Engine LITTLES_LAW_V1: exact decimal arithmetic written for ProcessWeave. No source code of other tools was copied. See the Little's Law algorithm document.