See it first: elapsed time and active work

Flow Analysis: elapsed time compared with active workTwo activities. Review application: Duration 120 minutes, Processing Time 30 minutes. Approve application: Duration 60 minutes, Processing Time 15 minutes. Elapsed time is 180 minutes; active processing is 45 minutes; the remaining 135 minutes are not automatically waiting time and the cause is not diagnosed.Illustrative processReview applicationDuration 120 · Processing 30 minApprove applicationDuration 60 · Processing 15 minElapsed time: 120 + 60 = 180 minElapsed 180 minActive processing: 30 + 15 = 45 minActive 45 minRemaining 135 min: cause not diagnosed
Figure. Illustrative example: 180 minutes elapsed but only 45 minutes of active work. Duration minus Processing Time is not automatically waiting time.

A case starts, goes through Review application (Duration 120 minutes, Processing Time 30 minutes) and Approve application (Duration 60 minutes, Processing Time 15 minutes), and completes. The elapsed time is 180 minutes but only 45 minutes are active work. What accounts for the remaining 135 minutes? Duration is elapsed activity time; Processing Time is active work. Duration minus Processing Time is not automatically waiting time, and Flow Analysis does not diagnose the cause for you. This is an illustrative example. The short names CT (180 minutes), TCT (45 minutes) and CTE (25.0 percent) come after the explanation.

Purpose

Understand how long the process takes, how much of that time is real work, and where elapsed time may be piling up.

How to use this analysis

Flow Analysis: the workflow in 5 stepsBoxes joined by arrows, left to right: 1. Choose the version; 2. Check the timings; 3. Check the routing; 4. Run; 5. Read the results.1Choose theversion2Check thetimings3Check therouting4Run5Read theresults
Figure. Flow Analysis: follow the numbered steps from left to right. The same steps appear on the page under “How to use this analysis”.

Choose a process and a scenario, enter your values and press Calculate. The result appears immediately below the button and the page moves it into view, so you never have to search for it. Read what it means, then enter a What-if in the What-if step and press Calculate What-if: its result and the comparison with the baseline appear directly underneath. You never have to scroll back up to calculate. Calculate What-if is a temporary experiment: it saves nothing, so you can change the figures and calculate again as often as you like. Choose Save as scenario only when you want to keep that What-if. In a Little's Law What-if, give two figures and the empty one is calculated (the baseline never fills it in); if you fill all three, choose which one to calculate. The page shows these same steps in the same order.

The same moves for every technique: the result appears right under the buttonSeven boxes joined by arrows: 1 Enter values, 2 Calculate, 3 Result appears immediately, 4 Understand the result, 5 Enter a What-if, 6 Calculate What-if, 7 Baseline vs What-if.1Entervalues2Calculate3Result appearsimmediately4Understand theresult5Enter aWhat-if6CalculateWhat-if7Baseline vsWhat-if
Figure. Visual walkthrough: enter values, calculate, read the result that appears right below, enter a What-if, calculate it in the same step and read the baseline against the What-if.

The steps, as they appear on the page

What you need: Flow Analysis needs a Duration and a Processing Time for each activity, and a probability for each decision or rework loop.

Step 1 — Choose the process version

Flow Analysis works on the BPMN version shown below. Pick another version from the process page if you need a different one.

Step 2 — Check activity timing

Duration is the elapsed time from the start to the end of an activity. Processing Time is the part of that time someone is actually working. Example: Review application: Duration 120 minutes, Processing Time 30 minutes.

Step 3 — Check routing information

Where the process splits or loops back, say how likely each way is. Example: 70% Approved, 30% Returned for correction.

Step 4 — Check readiness

The checklist shows what is ready and what is still missing.

Step 5 — Run Flow Analysis

Once everything is ready, the results appear below the inputs.

Step 6 — Interpret results

Average elapsed process time (CT), theoretical working time (TCT) and Cycle Time Efficiency (CTE) are explained next to the numbers.

A low Cycle Time Efficiency means most of the elapsed time is spent waiting rather than working. That suggests where to look first; it does not by itself show that a redesign is right.

Reading the results

  • Average elapsed process time (CT): how long a case normally takes from start to finish.
  • Theoretical working time (TCT): how much of that time is actual work.
  • Cycle Time Efficiency (CTE): working time as a share of elapsed time. A low value suggests a lot of waiting; it does not by itself show that a redesign is right.

The calculation itself is unchanged. The detailed Flow Analysis guide in the Flow Analysis category explains Duration, Processing Time and probabilities in depth.