Capacity Planner
How many people each role may need, which resource pool limits the process first and how busy each pool is.
See it first: staffing with people
Twenty cases a day create 900 minutes of Credit Officer work. Two Credit Officers, each planned for 336 effective minutes a day, offer 672 minutes, which is less than the workload. The modeled requirement is 2.68 FTE, so three whole people are indicated, one more than today. This does not mean the organization must hire one additional person. This is an illustrative example.
Purpose
Every case brings some work to the people or machines (resource pools) that carry it out. A pool has only so much working time per period. Capacity analysis compares the work one case brings with the time a pool has, and shows which pool can sustain the fewest cases per unit of time: the bottleneck. It also shows how busy each pool would be at your expected arrival rate, and what changes if you add a resource or change a probability.
How to use this analysis
Choose a process and a scenario, enter your values and press Calculate. The result appears immediately below the button and the page moves it into view, so you never have to search for it. Read what it means, then enter a What-if in the What-if step and press Calculate What-if: its result and the comparison with the baseline appear directly underneath. You never have to scroll back up to calculate. Calculate What-if is a temporary experiment: it saves nothing, so you can change the figures and calculate again as often as you like. Choose Save as scenario only when you want to keep that What-if. In a Little's Law What-if, give two figures and the empty one is calculated (the baseline never fills it in); if you fill all three, choose which one to calculate. The page shows these same steps in the same order.
The steps, as they appear on the page
What you need: The Capacity Planner needs the work per case (Processing Times and routing), who performs it, the demand, the working time per person and a target utilization. People now are needed only to check current staffing.
Step 1 — Confirm workload
See which activities bring work to the process, how often a case visits each (from the routing), and how much work that is per case. Processing Time is the active work, not the elapsed Duration.
Step 2 — Confirm who performs the work
Each resource pool is a card: who it is, which activities it performs, how many people it has now and how much working time each has. A lane can suggest a pool name, but it never tells us how many people are in it.
Step 3 — Set demand and working time
How many cases need to be handled in the planning period, and how much time each person works. Example: 20 applications per business day and 8 working hours per person per day.
Step 4 — Choose the planning target
Choose Can current staffing handle the demand? or How many people are needed?, and the target utilization: the share of working time you plan to use, leaving room for variation, breaks and meetings.
Step 5 — Calculate capacity or people needed
Press Calculate. Nothing is calculated until you do, and the result appears directly under the button.
Step 6 — Review bottlenecks and staffing gaps
Read the scenario bottleneck, the required FTE and whole people, current and planned utilization and any staffing gap for each pool.
Step 7 — Try a What-if
Start from +1 person, −1 person, more demand or faster work and press Calculate What-if. Nothing is saved unless you choose Save as scenario.
This is a deterministic planning estimate under the assumptions you enter: it is not a forecast and it does not model waiting (see Queueing Analysis). There is no universal target utilization: it is your planning assumption.
The result is a decision-support estimate under the assumptions you enter. It does not claim the best possible process and it does not predict waiting times; the Queueing technique looks at waiting, and the Token Game illustrates it.
Choosing a process
Open the technique from the Process Analysis menu and pick a process in the 'Choose a process' dropdown. It lists only the processes you are allowed to view. If two processes have the same name, the folder after the name tells them apart. Then choose the Open button. Moving to another technique keeps your choice.
Required inputs
- Processing Time of each activity (active work, not elapsed Duration).
- Expected visits of each activity per case (prepared from the routing, see below).
- Resource pools: how many resources, and the available working time per resource in the analysis period (for example 8 hours per day).
- Which pool does each activity, with the share and how many resources it needs at once; plus whether several pools are ALTERNATIVE or JOINT.
- The expected arrival rate (cases per hour, per day or per business day) and the analysis period the available time is stated for.
Prepared versus manually entered inputs
- Prepared from the BPMN: activity names, lanes (which may propose a pool name), Processing Time, and the routing with flow probabilities. These keep the source 'BPMN'. Prepared values are never changed in the diagram.
- Entered by you: the number of resources, available time, arrival rate, assignments and any missing Processing Time or probability. Each is stored as a scenario assumption with who entered it and when.
- A lane never implies a count of one: a pool's count must always be entered.
- A missing Processing Time is a data gap. The tool never replaces it with Duration; enter a value or an explicit assumption.
Step-by-step workflow
- Open the process and choose Process Analysis, then Capacity Planner.
- Confirm the workload: check the diagram's status on every activity, its Processing Time and the expected visits from the routing.
- Confirm who performs the work: each resource pool is a card with its people, working time, unavailable time and target utilization.
- Set the demand and the working time, then choose the planning target: current staffing or people needed.
- Press Calculate. The result appears directly under the button and the page moves it into view.
- Read the bottleneck, the required FTE and whole people, and the utilization now and at the required staffing.
- Enter a What-if in the What-if step and press Calculate What-if: the comparison appears directly below and nothing is saved.
- Choose Save as scenario to keep a What-if.
What the Capacity Planner can answer
- Staffing: how many people may be needed in each role?
- Capacity: can current staffing handle the expected demand?
- Bottleneck: which role is most likely to constrain modeled throughput?
These are estimates under the assumptions in the selected scenario. They are not optimisation, not certainty and never a mandatory staffing decision.
Process version, scenario and results
Every analysis scenario is bound to one exact process version and its BPMN fingerprint. The workload map, the side panel, the calculation and the Token Game all use that version, and the page shows its version and fingerprint. When the process moves on, a scenario on an older version is labelled HISTORICAL under the heading Process model updated: it keeps showing its own version so earlier results stay reproducible, and it is never rebound silently. Choose Create Capacity scenario from current v3 to make a new scenario on the current version; the historical one is not changed. ProcessWeave carries forward only what is safe (demand, working time, target utilization, roles and people), takes BPMN values from the new version and lists anything it cannot map under Needs review: new, removed or replaced activities, changed Sequence Flow endpoints, changed Processing Time or Duration, changed lanes and new or removed roles. Looking at a page never creates a scenario.
Given for this scenario and where the values come from
Before the steps, the Given section summarises the selected scenario and its exact version: the process and its lanes and routing patterns, the prepared roles and whether each came from a BPMN lane or was entered by a user, how many activities have a Processing Time and a Duration, the work information, and the scenario information (demand, planning period, available and unavailable time, target utilization and current staff). It then lists only what ProcessWeave still needs from you, or says READY. Each value has a data status: BPMN / PROCESS MODEL, OBSERVED, LOG-DERIVED, USER ENTERED, ASSUMED, DERIVED or MISSING. Values are never described as current performance unless they are observed or log-derived. A baseline is described as primarily based on scenario assumptions, as a mix of process-model data, derived values and scenario assumptions, or as including observed operational values.
Processing Time and Duration
Processing Time is the active work a resource needs; with the expected visits, assignment share and resources required it gives the staff work per case and drives every staffing figure. Duration is the elapsed time of the activity and is never used as staff workload. Where both exist, ProcessWeave shows the time beyond active processing (the Duration minus the Processing Time, never below zero) and the active-work ratio (Processing Time divided by Duration). The time beyond active processing is not automatically waiting time: it can be queueing, batching, an external dependency, calendar delay, system processing or a deliberate hold. If the Processing Time is longer than the Duration, the activity is marked NEEDS REVIEW and neither value is changed. If the Duration is missing, staffing still works and only this elapsed-time insight is limited. For each role the page shows the active staff work per case, the modeled elapsed activity time per case and the time beyond active processing per case; a large difference may warrant investigation and does not show that a shortage of staff caused it. To explore overall elapsed time and efficiency, open Flow Analysis; to explore resource waiting under queue assumptions, open Queueing Analysis. They run only when you open them.
Two ways to use the Capacity Planner
- Can current staffing handle the demand? Uses the people you have now to show workload, utilization, throughput capacity, the capacity gap and the bottleneck.
- How many people are needed? Uses demand, workload, available time and the target utilization to show required FTE, whole people, the difference from today and the utilization at the required staffing.
The workload map in Step 1
This workload map shows the exact BPMN process version attached to the selected analysis scenario. ProcessWeave overlays each activity with its Capacity Planning readiness: READY (Processing Time and resource assignment are available), ASSUMED (a scenario assumption is being used), MISSING (information must be provided before reliable staffing analysis) or NOT APPLICABLE (the element does not create human-resource workload). Each status is a word and a border pattern, never colour alone.
- Sequence Flows determine how often each activity is visited.
- XOR probabilities change how often alternative activities occur, and loops or rework repeat workload.
- Lanes may suggest organizational roles or resource pools. A lane never says how many people are available.
- The BPMN is read-only: analysis never changes it.
The table beside the map gives the work per case = expected visits x Processing Time x assignment share x resources required.
Zoom controls and the process-model panel
Above the map, Zoom Out, Zoom In, Fit Diagram and Reset Zoom move the view between 25% and 200% and show the current zoom. Zooming never changes the BPMN, the inputs or the results. On wide screens a View process model panel stays beside the steps while you work in Steps 2 to 8; it has Zoom Out, Zoom In and Fit Diagram, shows the same version and readiness as Step 1, and the Open the full model in Step 1 button takes you back. On narrow screens it is an ordinary expandable panel.
Collapsible steps
Every step header is a button: click it, or press Enter or Space, to open or close the step. Values you have typed are kept while a step is collapsed, and collapsing never saves or submits anything. ProcessWeave opens Step 1, the first step that still needs input and the steps that hold a result or an error; focus on a result or an invalid field opens its step automatically. Expand all steps and Collapse all steps are above the first step.
Pools, lanes and roles
A BPMN pool is the whole process; its lanes are usually roles. ProcessWeave prepares one candidate resource pool for each lane and assigns each activity to the pool of its lane, and you can review and correct this. A lane is not one person: the number of people, the working time per person, any unavailable time and the target utilization are always entered by you. If the BPMN has no lanes, ProcessWeave shows ORGANISATIONAL INFORMATION NEEDED: it does not assume one actor does everything. Create the resource pools yourself, or analyse a model whose lanes represent roles.
Resource-pool cards
A BPMN lane can suggest a pool's name. It never suggests how many people the pool has: the number of people, the working time per person and any unavailable time are always entered by you.
Target utilization
What proportion of available working time should be planned as usable capacity? Examples: 80%, 85% or 90%. The target leaves time for variation, breaks, meetings, interruptions and other work. There is no single correct target. If you do not set one, ProcessWeave uses 80% and marks it ASSUMED.
How many people are needed: the staffing formulas
| Quantity | Plain meaning | Formula |
|---|---|---|
| Workload | Work the demand brings to the pool in one period | demand x sum of (expected visits x Processing Time x share x resources required) |
| Net available time | Working time one person really has | working time per person - unavailable time per person |
| Effective capacity | Usable time per person at the target | net available time x target utilization |
| Required FTE | Full-time equivalents needed | workload / effective capacity per person |
| Required whole people | People to employ | ceiling(required FTE); the FTE is not rounded before the ceiling |
| Current utilization | Share of available time used now | workload / (people now x net available time) |
| Planned utilization | Share used at the required staffing | workload / (required whole people x net available time) |
Worked staffing example
The same example with people. Twenty cases a day create 900 minutes of Credit Officer work. Two Credit Officers, each planned for 336 effective minutes a day, offer 672 minutes, which is less than the workload. The modeled requirement is 2.68 FTE, so three whole people are indicated, one more than today. This does not mean the organization must hire one additional person; it means the stated workload and planning assumptions correspond to about 2.68 FTE, which needs three whole resources if the work is staffed only with whole people. The role summary in the figure (Application Clerk 2, Credit Officer 3, Supervisor 1, Records Officer 1) is illustrative: the Capacity Planner estimates each resource role separately, so one role may need more capacity while another has spare capacity. A Review application activity with a Duration of 120 minutes and a Processing Time of 30 minutes leaves 90 minutes beyond active processing; Processing Time drives staff workload, Duration gives elapsed-time context, and the remaining time is not automatically classified as waiting.
- Demand: 20 cases per day. Credit Officer work: 45 minutes per case, so the workload is 900 minutes per day.
- Available per person: 420 minutes per day. Target utilization: 80%, so the effective capacity is 336 minutes per person per day.
- Required FTE: 900 / 336 = 2.68. Required whole people: 3.
- Under this scenario, two Credit Officers provide less capacity than the workload implied by the demand: their utilization now would be 900 / (2 x 420) = 107%. If these assumptions hold, three Credit Officers would bring it to 900 / (3 x 420) = 71%, within the selected 80% target.
Role-based staffing: the multi-lane worked example
Take the synthetic Multi-lane Credit Application: one pool with four lanes, 20 cases per business day, 7 working hours per person per day and an 80% target. Every Processing Time and probability in it is a transparent synthetic assumption, not observed organisational data. Expected visits make Check completeness 1 / (1 - 0.1) = 1.11 per case (10% rework) and the supervisor activities 0.2 per case (20% high risk).
| Role | Work per case | Current staff | Required FTE | Recommended whole staff | Difference |
|---|---|---|---|---|---|
| Application Clerk | 31.7 min | 2 | 1.88 | 2 | 0 |
| Credit Officer | 55 min | 3 | 3.27 | 4 | +1 |
| Supervisor | 6 min | 1 | 0.36 | 1 | 0 |
| Records Officer | 15 min | 1 | 0.89 | 1 | 0 |
Under this scenario, the modeled Credit Officer workload exceeds the selected 80% target with three staff. The calculation indicates 3.27 FTE, corresponding to four whole staff, and the Credit Officers are the scenario bottleneck. This is a calculated staffing indication for this scenario, not a mandatory real-world staffing decision.
What the result rests on
A staffing indication is based on the selected scenario's expected demand, Processing Times, expected activity visits, routing and rework probabilities, activity-to-role assignments, working time, unavailable time, target utilization and current number of people. ProcessWeave says which of these are scenario assumptions and which are supplied or observed values; it never presents assumptions as measured performance.
Reading the result and trying a What-if
At the top of Step 6, the Staffing indication shows each role's current staff, required FTE, recommended whole staff and difference, then the overall scenario bottleneck, a chart of current against recommended staff, and a role-by-role table with utilization now and at the recommended staffing, modeled throughput capacity, capacity gap and each role's share of the workload. View calculation details holds the formulas.
A What-if is a temporary experiment. In Step 7 you can set the people in each role (for example Credit Officers 3 to 4, Application Clerks 2 to 1), change demand, the target utilization, working time or Processing Time, and press Calculate What-if: the role-by-role comparison appears immediately and nothing is saved. Choose Save as scenario only for the What-if you want to keep; a saved scenario can be opened in the Token Game.
The Capacity Planner is a deterministic planning calculation. The Token Game is an illustrative scenario run that shows queues forming; it never changes the planning result and it never switches scenario silently.
How it is calculated
| Quantity | Plain meaning | Formula |
|---|---|---|
| Unit load | Resource-seconds one case needs from a pool | sum of expected visits x Processing Time x share x resources required |
| Available capacity | Working seconds the pool offers per period | number of resources x available seconds per resource |
| Theoretical throughput | Most cases per second the pool could sustain | available capacity / (unit load x analysis period) |
| Utilization | Share of that throughput the demand would use | arrival rate / theoretical throughput |
| Capacity gap | Spare (positive) or missing (negative) throughput | theoretical throughput - arrival rate |
| Bottleneck | The pool that limits the process first | the pool with the lowest theoretical throughput |
Expected visits come from the routing probabilities: a gateway that sends 30% of cases one way and 70% the other gives those activities 0.3 and 0.7 visits per case. A loop that repeats with probability 0.2 gives the activity 1 / (1 - 0.2) = 1.25 visits. Parallel (AND) branches each run once per case. Loops are solved exactly without simulating cases.
Worked BPMN example
A request is checked (10 minutes) by Clerks and then, in 50% of cases, approved (5 minutes) by Managers. There are 2 clerks and 1 manager, each with 8 hours (28,800 seconds) per day, and cases arrive at 40 per day.
- Clerks: unit load = 1 x 600 s = 600 s; capacity = 2 x 28,800 = 57,600 s per day; throughput = 57,600 / 600 = 96 cases per day; utilization = 40 / 96 = 41.7%.
- Managers: unit load = 0.5 x 300 s = 150 s; capacity = 28,800 s per day; throughput = 28,800 / 150 = 192 cases per day; utilization = 40 / 192 = 20.8%.
- Under this scenario the Clerks have the lowest throughput (96 per day), so this estimate suggests they limit the process first.
What-if example
Raise arrivals to 120 cases per day. The Clerks' utilization becomes 120 / 96 = 125%, and the tool shows: 'Demand exceeds calculated theoretical capacity for this resource pool under the current scenario.' Adding one clerk raises their throughput to 144 cases per day. Adding one resource would be expected to lower utilization to 83%. The comparison table shows unit load, capacity, utilization, gap and the bottleneck before and after.
Assignments: ALTERNATIVE versus JOINT
- ALTERNATIVE: the pools can each do the activity; the shares must add up to 1 (for example 60% of cases handled by Team A, 40% by Team B). Each pool carries only its share.
- JOINT: every listed pool is needed together for each execution (for example a doctor and a room). Every share is 1, and each pool carries the whole load.
- Mixed or ambiguous assignments are rejected with a message; a joint requirement is never treated as alternatives.
When the process model is updated
A scenario belongs to one exact version of the process and never changes version by itself, so its results can always be reproduced. When the process gets a newer version, pages opened with an older scenario say so: 'Process model updated', with both version numbers. Choose Create scenario from current version to make a new scenario on the newest version. Your resource pools, arrival rate and calendar are copied; values tied to a step or flow are copied only when that same step or flow still exists and joins the same elements. Anything else is listed under Needs review for you to check. The old scenario stays as it was.
Interpreting the results
- Utilization below 100% suggests the pool can keep up on average; close to 100% leaves little room for variation, and queues are expected to grow.
- At or above 100%, the tool warns that demand exceeds the calculated theoretical capacity of that pool under the current scenario.
- The bottleneck depends on the numbers you entered. Changing a count, a probability or a Processing Time can move it to another pool.
- The estimate suggests where to look first; it does not say what to do.
Assumptions
- Steady state: demand and available time are averages over the analysis period.
- Work is spread evenly and resources are interchangeable within a pool.
- Expected visits come from the stated probabilities, which are assumed to be independent of one another.
- Processing Time is the active work only; waiting time is not part of the load.
- Available time already allows for breaks, leave and other non-working time as you entered it.
Limitations
- No waiting time or queue length is calculated here (see Queueing Analysis).
- Variation in arrivals and work times is not modelled in the capacity estimate.
- Unstructured parallel blocks, loops that never end and missing probabilities are reported as such; no numbers are invented for them.
- Resource counts and available time are not read from organisation records; they come from your scenario.
Provenance
The capacity method follows the resource-analysis chapter of Dumas, La Rosa, Mendling and Reijers, 'Fundamentals of Business Process Management' (quantitative process analysis), and standard operations-management capacity analysis. Expected visits use the classical traffic equations of a routing (Markov) model. The Token Game is an original explanatory simulation inspired by the token game idea of Petri nets, as taught in the WoPeD papers; no WoPeD source code is used. Algorithm documents: docs/process-analysis/02-capacity-bottlenecks.md and 04-token-game.md.